Avino commences construction of new Tailings Storage Facility - "The new TSF is being constructed by Desarrollos ROD, S.A. de C.V. who are recognized as one of the premier contractors in Mexico for tailings related projects. The new TSF will cover 21 hectares and will be able to store 7.5 million tons of wet tailings. The TSF will be built in 4 stages; the first 2 stages, which are expected to take approximately 6 months to complete, have an estimated cost of US$2.2 million and will provide enough capacity for 6 operating years." More