Jaguar Announces Successful Recommissioning of Mill #3 at Turmalina Gold Mine - "The reconstruction of Mill #3 commenced in April 2016 , at a total estimated capital cost of US$1.34 million (approximately R$5.09 million ), funded from operating cash flow. Mill #3 was fully commissioned on December 28, 2016 with an estimated installed capacity of 1,600 tonnes per day or 580,000 tonnes per year." More