Pretium Resources Inc.: Brucejack Commissioning Accelerated; Forecast to Complete Mine Construction is US$811.1 million - "Pretium Resources Inc. (PVG)(PVG) ("Pretivm" or the "Company) is pleased to report the acceleration of commissioning of the Brucejack Mine with dry commissioning now scheduled to commence in March and wet commissioning scheduled to commence in early April. In addition, an updated forecast of the capital cost to complete construction of the Brucejack Mine has been completed. The capital cost, including working capital, is now estimated to be US$811.1 million, an increase of 16% from the February 2016 capital cost estimate." More